Free questions and answers on project integration management: Test includes questions from Project Integration Management knowledge areas, including seven processes of Project Integration Management.
Total
Questions: 30 Time
Allowed: 35 Min
Try to
Achieve: 24 (80 %) for better scorer in real PMP Examination at One Go
(In real PMP
Exam, 200 random questions will be asked- Duration: 4 Hours)
Best of Luck
Practice Test Questions- Project Integration Management
1. Which of
the accompanying would not be viewed an Enterprise Environmental Factor during
the Develop Project Charter process?
A. Scope
Statement
B. Organizational
infrastructure
C. Governmental
standards
D. Marketplace
conditions
2. The
Close Project or Phase process isn’t performed when:
A. Cancelling
projects
B. Closing
projects
C. Closing
project phases
D. Reactivating
projects
3. Which of
these tools and techniques is basic to every one of the seven Project Integration Management processes?
A. Meetings
B. Data
analysis
C. Data
gathering
D. Expert
Judgment
4. What is
a prescribed strategy for controlling change within a project?
A. Have just
the project manager able to initiate change.
B. Have
each change approved or rejected through a formal change control process.
C. Permit
each project member ultimate control of changes within their realm of the
project without a review process.
D. Freeze
scope and allow no changes.
5. A
project manager calls you in as a consultant to give input on developing the
Project Charter. As per the PMBOK, your contribution to the project could best
be named as:
A. Professional
Consultant
B. Expert
Judgment
C. Charter
Consultant
D. Expert
Consultancy
6. Which
process is concerned with providing forecasts to update current cost information?
A. Monitor
and Control Project Work
B. Project
Management Information System
C. Close
Project or Phase
D. Direct
and Manage Project Work
7. You are starting
a new project. When would it be advisable for you to utilize the Perform
Integrated Change Control process?
A. Throughout
the entire project
B. Only
when closing out the project
C. Only
after the project is completely funded
D. Only
after the project scope is clearly defined
8. The
project management team has discovered that there are few changes to the scope
of the project. As per PMBOK, who is responsible for reviewing, evaluating, and
approving documented changes to the project?
A. Change
Control Board (CCB)
B. Change
Configuration Board (CCB)
C. Scope
Control Board (SCB)
D. Configuration
Control Board (CCB)
9. Difference
between the Monitor and Control Project Work process
and the Direct and Manage Project Work process is:
A. The
Monitor and Control Project Work and the Direct and Manage Project Work
processes are the equivalent.
B. The
Monitor and Control Project Work process monitors the project performance
while the Direct and Manage Project Work process is concerned
with performing the activities to accomplish project requirements.
C. The
Monitor and Control Project Work process is a sub-process of the Direct
and Manage Project Work process.
D. There is
nothing of the sort as the Monitor and Control Project Work process.
10. You are
a consulting project manager and an speculation bank has a contract with you to
run a large information technology project that is expected to last 15 months.
During the Direct and Manage Project Work process, you discover that several
regulatory requirements were addressed in the project management plan but
missed from the scope statement. Inability to meet these requirements could
result in legal action against the organization. However, implementing the
technology to comply with these regulations could exceed the budget and scope
of the project and result in the cancellation of the project. What would it be
a good idea for you to do?
A. Try not
to do anything as these requirements are not a part of the scope baseline.
B. Request
additional funds to implement these requirements.
C. Submit a
change request to incorporate the missed requirements in the project's scope.
D. This is
a classic example of scope creep and such requirements must be ignored.
11. Your
project team is well in progress with the development of the product of the
project. A portion of the work has progressed and some deliverables have been
reviewed by key stakeholders. During a deliverables review, one of the
stakeholders found a discrepancy in one of the deliverables that needed to be
addressed immediately. The team reviewed the stakeholder’s issue and agreed
that some action needed to be taken to bring the deliverable back into
compliance. The best definition for this activity is called:
A. Defect repair
B. Corrective action
C. Quality control
D. Preventive action
A. Defect repair
B. Corrective action
C. Quality control
D. Preventive action
12. What
is the difference between a configuration management system and a change
control system?
A. The configuration management system is part of the PMIS - the change control system is not
B. The change control system is part of the key PMIS - the configuration management system is not
C. The change control system feeds into the configuration management system and is part of the configuration management system
D. Both the change control system and a configuration management system are organizational process assets
A. The configuration management system is part of the PMIS - the change control system is not
B. The change control system is part of the key PMIS - the configuration management system is not
C. The change control system feeds into the configuration management system and is part of the configuration management system
D. Both the change control system and a configuration management system are organizational process assets
13. The
project management plan is finished and is ready to be baselined. Be that as it
may, a key stakeholder just found a critical exclusion and requests an
adjustment to the project management plan. What would it be a good idea for you
to do next as the project manager?
A. Implement a formal CR
B. Make the adjustment
C. Consult the change control board
D. Inform the stakeholder that this constitutes scope creep and refuse to make the change
A. Implement a formal CR
B. Make the adjustment
C. Consult the change control board
D. Inform the stakeholder that this constitutes scope creep and refuse to make the change
14. Bernard is the project manager of a $200
million construction project. The project is in the execution phase. In the
last review meeting, several stakeholders looked disappointed and have
indicated the need for changes to the requirements set. They were of the conclusion
that these components were missed in the initial requirements collection
process. Therefore, change requests were raised to add these components to the
project. In this case, change requests will be an input to which of the
following processes?
A. Control Scope
B. Monitor and Control Project Work
C. Define Scope
D. Perform Integrated Change Control
B. Monitor and Control Project Work
C. Define Scope
D. Perform Integrated Change Control
15. Mitch is delegated as the project manager for a
software development project. His organization follows a matrix organization
structure and he is required to negotiate and acquire the necessary resources
for the project from the functional managers. However, when he moved toward a
functional manager for a discussion, he was surprised that such a project
exists in the organization. In what manner will he persuade him to acquire the
necessary resources for his project?
A. He will try to explain to him why the project
was initiated and what are the benefits of the project to the organization and
how functional managers are pivotal to the success of the project.
B. He will ask him to speak to the sponsor, who assigned him the project.
C. He will show him a document that formally authorizes him to apply organizational resources to project activities.
D. Since he is working in a strong matrix organization structure, he will instruct the functional manager to just comply with your requirements.
B. He will ask him to speak to the sponsor, who assigned him the project.
C. He will show him a document that formally authorizes him to apply organizational resources to project activities.
D. Since he is working in a strong matrix organization structure, he will instruct the functional manager to just comply with your requirements.
16. Coming up next are the key advantages of the
Develop Project Charter process EXCEPT:
A. It gives a direct link between the project and
the strategic objectives of the organization.
B. It creates a formal record of the project.
C. It defines the product, service or result boundaries, and acceptance criteria.
D. It demonstrates the organizational commitment to the project
B. It creates a formal record of the project.
C. It defines the product, service or result boundaries, and acceptance criteria.
D. It demonstrates the organizational commitment to the project
17. Which of the accompanying explanations isn't true
about projects?
A. The project charter establishes a partnership
between the performing and requesting organizations.
B. Projects are initiated by an entity internal to the project.
C. Projects are initiated due to internal business needs or external influences.
D. A project charter isn't viewed as a Contract.
B. Projects are initiated by an entity internal to the project.
C. Projects are initiated due to internal business needs or external influences.
D. A project charter isn't viewed as a Contract.
18. Shoibal has recently joined as the project
manager for a hotel building project. During the introduction meeting with the
sponsor, he hands over a document to him. He also warns him that he should not
update or modify the document. The document describes the necessary information
from a business standpoint to determine whether the expected outcomes of the
project justify the required investment. Which of the accompanying documents
did the sponsor give him?
A. Agreement
B. Business case
C. Benefits management plan
D. Project charter
B. Business case
C. Benefits management plan
D. Project charter
19. You are in the process of developing the
project charter for an telecom project. Which of the following is NOT a typical
element found in the project charter?
A. Acceptance criteria
B. Project approval requirements
C. Project exit criteria
D. Measurable project objectives and related success criteria
B. Project approval requirements
C. Project exit criteria
D. Measurable project objectives and related success criteria
20. The project kick-off meeting is generally connected with the end of
planning and start of executing. As the project manager, you will utilize the
kick-off meeting for all of the following outcomes EXCEPT:
A. To communicate the objectives of the project.
B. To gain the commitment of the team for the project.
C. To explain the roles and responsibilities of each stakeholder.
D. To formally authorize the existence of the project
B. To gain the commitment of the team for the project.
C. To explain the roles and responsibilities of each stakeholder.
D. To formally authorize the existence of the project
21. Which of the accompanying best possible job
role of the project manager as related to changes?
A. Make changes as and when it occurs.
B. Estimate the impact of the change on the project objectives.
C. Prevent unnecessary changes.
D. Notify senior management about changes
B. Estimate the impact of the change on the project objectives.
C. Prevent unnecessary changes.
D. Notify senior management about changes
22. The project charter has been developed and the
project has been formally authorized. A full-time project manager is selected
for the project. There is clarity about the business needs, high-level project
description, and product requirements that the project is to address. A summary
budget has also been approved. Given this information, what activity should the
project manager perform NEXT from the accessible choices?
A. Perform the work defined in the project
management plan to achieve the project`s objectives.
B. Define, prepare and coordinate all subsidiary plans and integrate them into a comprehensive project management plan
C. Monitor and report the progress to meet the performance objectives defined in the project management plan.
D. Define scope and get the project scope statement so that you can understand how much effort is needed for the project
B. Define, prepare and coordinate all subsidiary plans and integrate them into a comprehensive project management plan
C. Monitor and report the progress to meet the performance objectives defined in the project management plan.
D. Define scope and get the project scope statement so that you can understand how much effort is needed for the project
23. John is recently been assigned to work with
another certified PMP on a large project. He heard from a colleague that this
other project manager’s practices, are often in violation of the PMI Code of
Ethics and Professional Conduct. What should he do NEXT?
A. Report him to PMI as this forms part of your
professional ethics and responsibility
B. Report this to the project sponsor as he should inform the organization before approaching PMI
C. Do nothing since the project manager is not doing anything contrary to the company’s policies
D. Evaluate the credibility of your colleague’s statements before taking any action
B. Report this to the project sponsor as he should inform the organization before approaching PMI
C. Do nothing since the project manager is not doing anything contrary to the company’s policies
D. Evaluate the credibility of your colleague’s statements before taking any action
24. Jerome, a
project manager in a software Company got all the project related information
listed and improvised in the Organizational Process Assets. The process
undertaken by him is known as:
A.
Monitoring and
Controlling Project Work
B.
Closing Project or Phase
C.
Perform Integrated
Change Control
D.
Directing and Managing
Project Work
25. During directing and managing a project, a
project manager is utilizing some tools and techniques. The tools and
techniques guiding him do exclude.
A.
Change Control Tools
B.
Expert Judgement
C.
Project Management
Information system
D.
Meetings
26. Monitor and Control Project Work is a process which
utilizes various inputs for detecting and correcting the shortcomings in any of
the areas to guarantee accomplishment of the objectives of the project. Which
of the following inputs is used for the process?
A.
Agreements
B.
Approved Change Requests
C.
Validated Changes
D. Accepted Deliverables
D. Accepted Deliverables
27. You are a project manager of T-Telecom
Company and you are assigned to a project that has already decided to
outsource. As a project manager, you have to organize a formal bid process and
select the vendor. You own stock in one of the vendor organization also
participated in the bidding process. What is the BEST strategy for you?
A. Get the vendor company selected for the project.
B. Keep the information to yourself.
C. Tell your manager and remove yourself from the vendor
selection committee.
D. Ask other members of
the selection committee to select your vendor company.
28. Which of coming up next isn’t the
input of Direct and Manage Project Execution process?
A. Project
Management Plan
B. Approved
change requests
C. Enterprise
Environmental Factors
D. Project
charter
29.
You are project manager of software-based organization. You are taking over a
project during the planning process group and find that many individuals have
signed the project charter. Which of the accompanying should MOST concern you?
A.
Who will be a member of the change control board.
B.
Who are the stakeholders for the project.
C.
Need to spend more time on configuration management.
D.
Determining the reporting structure.
30.
A project manager is selected to head a highly technical project in an area
with which this person has limited familiarity. The project manager delegates
the processes of develop schedule, define activities, and estimate activity
resources to various project team members, and basically serves as an
occasional referee and coordinator of activities. The results of this approach
are likely to be:
A.
A team functioning throughout the project at a very high level, demonstrating creativity
and commitment
B.
A team that initially experiences some amounts of confusion, but that after a
period of time becomes a cohesive and effective unit
C.
A team that is not highly productive, but that stays together because of the
work environment created by the project manager
D.
A team that is characterized by poor performance, low morale, high levels of
conflict, and high turnover
Free questions and answers on project integration management
Answers
with Explanations
1. A - The
scope statement is clearly not an enterprise environmental factor, whereas the
other three choices—governmental standards, organizational infrastructure, and
marketplace conditions—are enterprise environmental factors.
2. D - The
Close Project or Phase process allows the project manager to close or finish a
specific phase of the project.
3. D - All
seven processes of Project Integration Management use Expert Judgment as a tool
and technique.
4. B - The
change control procedure varies from project to project. However, every change
request must be processed through a formal change control process.
5. B -
Expert Judgment is judgment provided, based on expertise in an application
area, a knowledge area, a discipline, an industry, etc. Expert Judgment is
available from many sources including consultants.
6. A -
During the Monitor and Control Project Work process, work performance data is
gathered and passed to the controlling processes. The Monitor and Control
Project Work process is responsible for keeping track of the all project's
measures, including cost.
7. A -
Changes can occur in the project at any time. The Perform Integrated Change
Control process is valuable for managing and tracking those changes.
8. A - The
Change Control Board is a group of formally constituted stakeholders responsible
for reviewing, evaluating, approving, delaying or rejecting changes to the
project.
9. B - The
Monitor and Control Project Work process monitors the other project processes
including the Direct and Manage Project Work process, while the Direct and
Manage Project Work Process completes the project scope.
10. C - All
regulatory requirements must be met. Doing nothing or considering this a scope
creep are not valid options. You would have to request additional funds, but first
you need to submit a change request for approval. A change request can be
submitted as a part of the Direct and Manage Project Work process.
11.
A - Did you think it was a corrective action? Corrective
actions are taken to bring the project into line at some future point. Defect
repairs address immediate concerns
12. C – A and B
are deliberate misdirection. D is incorrect. The change management system is
subsumed within the configuration management system
13. B – Prior to
baseline, the PM plan can be adjusted without a CR, consulting the change
control board, or addressing a scope creep issue.
14. D - Change Requests
can be an input to only one process, which is Perform Integrated Change
Control. Change Request, wherever generated in the project, has to be an input
to this process. Please remember that only Perform Integrated Change Control
process can review and approve/ reject the change requests.
15. C - Project Charter
is the document that authorizes the existence of a project and empowers the
project manager to obtain resources for the project. So, the project manager
should show the project charter, which should convince the functional manager.
16. C - Describing the
product, service or result boundaries, and acceptance criteria is the benefit
of Define Scope Process. The remaining are all the benefits of Develop Project
Charter process.
17. B - Projects are
initiated by an entity external to the project such as a sponsor, program or
project management office (PMO), or a portfolio governing body chairperson or
authorized representative.
18. B - The business
case describes the necessary information from a business standpoint to
determine whether the expected outcomes of the project justify the required
investment.
19. A - Acceptance
criteria is included as part of Project Scope Statement, while the other three
are typically seen in Project Charter.
20. D - Formal
authorization of a project happens at the time of project charter, not at the
kick-off meeting.
21. C - While you might
be carrying out all the other choices with regards to change requests, the most
important role of project manager is to work towards preventing unnecessary
changes in the project.
22. B - From the
question, you can understand that the Project Charter has already been
developed. Next step is to develop the project management plan.
23. D - As per the PMI
Code of Ethics and Professional Conduct, you should bring violations of the
code to the attention of senior management at the company and possibly PMI.
However, you should get the facts together and gather evidence before taking
either of those steps.
24.
C- Refer
to Perform Integrated Change Control
25. A- Change Control Tools are used in Perform
Integrated Change Control process
26. C - See Monitor and Control Project Work inputs
27. C - Best Option is tell your manager
and remove yourself from the vendor selection committee.
28.
D - Project charter is not input of Direct and Manage Project Execution
process. Inputs of Direct and Manage Project Execution process are : Project Management
Plan , Enterprise Environmental Factors, Approved change requests AND
Organizational Process Assets.
29.
C - Because of many individual signed in project charter, areas concerned with
this project is many. you should be concern with communications requirements,
competing needs and requirements impacting your efforts on configuration
management.
30. D – A project
manager must manage and integrate all aspects of a project. If all activities
are delegated and team members will spend more time jockeying for position than
completing activities.
Conclusion
Most hopefully, you would like
this information, and this will be more beneficial for you.
The questions and answers provided
above on Project Integration management will help you preparing examination.
If you
don’t agree with any of the answers above, feel free to post your views here. Share your views/questions about this script in the comment box below
which would be highly appreciated. Let
us discuss and come to a conclusion.
----------------------------------------------------------------------------------------------------
Thank you for taking time reading this
article.
I scored 22 out of 30 questions. Also, I improved my knowledge on integration management. Thanks for sharing. Please share questions on scope management.
Reply